Timeline for completion of action items from Sediment Transport Workshop

For more information, contact: csherwood@usgs.gov (508) 457-2269

Tasks Person Target Date
Submit final version of workshop report to USGS Sherwood Oct. 24, 2000
Develop test cases:
  • Brainstorm for ideas; develop a list of ideas. 
Sherwood
Signell
Harris
Nov. 3, 2000
  • Incorporate input from steering committee 
Sherwood
Signell
Harris
Jan. 15, 2001
  • Define and document initial suite of test cases on web site 
Sherwood
Signell
Harris
Jan. 22, 2001
Model evaluation:
  • Fill out table listing the properties of available models. 
Signell
Harris
Sherwood
Nov. 11, 2000
  • Incorporate input from modeling community / steering committee 
Signell
Harris
Sherwood
Jan. 11, 2001
Run test cases:
  • ECOMSED 
Harris Feb., 2001
  • EFDC 
Sherwood
Signell
Feb., 2001
  • DELFT-3D 
Sherwood Feb., 2001
  • ROMS 
Signell April, 2001
  • COHERENS 
Sherwood April, 2001
  • Publish summary results. 
Sherwood
Signell
Harris
Oct., 2001
Form steering committee
  • Put together a preliminary list, decide how big the committee should be. 
Signell
Harris
Sherwood
Nov. 13, 2000
  • Solicit nominations from mailing list; MEM list; etc. 
Signell
Harris
Sherwood
Dec 13, 2000
  • Choose the final committee 
Signell
Harris
Sherwood
Dec. 20, 2000
   

 